Docs/Records, Defects, and Renewals

Checks and Records

Checks and records trace a gas safety check from schedule through mobile capture, review, generation and delivery.

For: Office teams and engineers16 min read7 sections

Interactive lifecycle explorer

Switch between record types to understand what each status means before changing operational state.

  1. 1DraftBeing prepared and not yet scheduled.
  2. 2To bookTaken on, not yet dated: on the To book list and on no engineer’s run until a date books it.
  3. 3ScheduledAssigned to an engineer with a date and band.
  4. 4In progressThe engineer has started capturing on site.
  5. 5SubmittedCapture is complete. The engineer’s run lists it under Sent for review; the office reads Awaiting senior review while a senior review waits.
  6. 6Record generatedA record has been produced from the reviewed check.
  7. 7Action requiredA senior reviewer has returned the check for changes (the office reads Changes requested), so it stays open until the engineer updates it and the review is approved.
  8. 8CompletedClosed out. A no-access visit also closes here and reads No access.
  9. 9No accessThe engineer could not get in: no certificate is made and the property stays due until another visit.
  10. 10CancelledThe check was called off and will not be carried out. A check with an issued certificate cannot be cancelled.
Review exampleCustomer-safe walkthrough

Review submitted checks before they become records

The office review queue is where quality is enforced. A record is immutable once generated, so review carefully before generating.

What you see

  • The Gas safety checks list filtered by Status to Submitted, sorted by the Date column.
  • On the check, Findings & evidence: Engineer findings, Appliance results with their readings, and Defects raised.
  • A Certificate type selector beside the Generate button (Generate CP12 for a landlord record) that produces the immutable record.

How to use it

  • Filter to Submitted, sort by date, and work oldest first.
  • Confirm each appliance has the readings its type requires.
  • Resolve anything ambiguous with the engineer before generating.
  • Generate the record only when the evidence is complete and defensible.

Work Gas safety checks

Gas safety checks

Status: Submitted · oldest first

+ Schedule check

12 Oakwood Road

A. Mercer

1h ago2 applsSubmitted

3 Mill Court

J. Patel

1h ago4 applsAwaiting senior review

88 Vale Street

A. Mercer

1h ago1 applDefect: ID
Generate CP12Request changes

Decision guide

SituationA reading is missing
Recommended actionIf the engineer requested a senior review, use Request changes to return it; otherwise agree the correction with the engineer and have them resubmit.
Proof it workedThe resubmission includes the reading.
SituationA defect needs a category
Recommended actionConfirm AR, ID, or NCS before generating.
Proof it workedThe record shows the correct category.
SituationEverything checks out
Recommended actionGenerate the record and deliver it.
Proof it workedTenant and client delivery stamps appear.

Troubleshooting path

  1. 1If generation is blocked, read the reason after Not ready to generate under the button: the check has no overall result, an appliance has no result, a Satisfactory verdict conflicts with an unsafe appliance, a CP12 has no landlord or agent address, or a senior review is still open. A used-up monthly record allowance is reported when you press Generate.
  2. 2If a record is wrong, correct the source data and complete a new check; a record cannot be regenerated.
  3. 3If a check is missing from the queue, confirm it was submitted rather than left in draft.

Check Lifecycle

  1. 1Confirm the property and appliance register are current.
  2. 2Schedule the check and assign an active engineer. The check page shows one Engineer: who did the work. Where the person it was booked for is someone else (the certificate names a different engineer), a Booked for field beside it names the assignee, and the Work cards show Booked for under the engineer’s name in the same case.
  3. 3Also a boiler service, on Schedule check, books a boiler service on the same visit: it shows the boiler on the property’s register, asks Service kit needed? (Yes or No, which Schedule check needs before it saves), and a visit given a start time and no end time is booked for an hour and a half instead of the usual hour. The engineer’s check says the service is due too, the check page shows Boiler service under Visit details, and once the CP12 is made the certificate control starts on the Gas Service Record. Anyone who works alone, whose Submit makes the CP12, gets the service record made with it.
  4. 4More than one piece of work can go on the same visit, any firm and any mix: a check and a boiler service, a repair and a service, an installation and its commissioning, or two jobs. Also a boiler service adds the service as a job of its own on the check’s visit, and Add work to this visit, under On this visit on a check’s or a job’s page, adds any other job: the same engineer, slot and property. The engineer booked on the visit adds work too, from the check’s done screen or the finished check on the day, such as a repair found while they were there (see Mobile Check Capture). Each piece keeps its own record or report, close reason and invoice line. Moving the visit, or changing its engineer, moves everything on it; Book separately takes one piece off to book it for another time. A service booked with a check is done on the check: the check submitted with access (or its Gas Service Record) completes it and moves the next boiler service date. A visit with more than one piece of work goes on one invoice that the office raises, so the engineer’s phone offers no Invoice now for it. No access on the check records no access for everything on the visit, and no certificate is made.
  5. 5The engineer captures readings, defects, photos, and signatures from My day on their phone, then submits.
  6. 6The office reviews the submitted check and generates the gas safety record.
  7. 7Deliver the record to the tenant and client and schedule any renewal or remedial follow-up.
  8. 8Bill the visit with Invoice this job at the top of the check page: it raises a draft invoice for the customer and the property (see Invoices) A visit with more than one piece of work gets one invoice with a line for each finished piece, priced by its own work; a piece billed to someone else, or finished after the invoice was raised, gets an invoice of its own.
  9. 9For next time, under the check page’s heading, lists the property’s notes kept for next time and its field notes marked Important (a flue within 300 mm of a window, say), so the office sees what the engineer was told. They are kept on the property (see Property Management) and nothing in them goes on the certificate by itself.
  10. 10Book the property’s next check with Book the next check at the top of a completed check, one whose certificate is issued, or imported history: it opens Schedule check with the property already chosen. An open check does not offer it, and a no-access visit offers Book another visit instead.
  11. 11A check’s appliances are added to it when the engineer records it on the phone, from the property’s appliance register. Until then, Appliance results on the check page says how many the register holds, for example No appliances on this check yet. The property’s register has 4 appliances, with Record on mobile for those who record checks.

Check Statuses

Checks live under Work, then Gas safety checks, in the menu. Each one moves through a fixed set of statuses. The Certificate type selector and Generate button appear while a check is Submitted, In progress, Action required, Record generated or Completed, so a CP14 or service record can be added after the CP12; they never appear on imported history.

  • Save this list as a report, at the top of Gas safety checks for owners and office, saves the search, status, engineer and date filters on screen as a report with the columns you choose, for example the checks booked in the next 7 days, emailed to the office every Monday. See Saved Reports and Scheduled Emails.
  • Draft, To book, Scheduled, In progress, Submitted, Record generated, Action required, Completed and Cancelled are the check statuses; the Status and Lifecycle Reference explains each one. A booked check that is past its date and not done reads Visit overdue beside its status, in the Gas safety checks list and on its own page.
  • To book is a check logged with no date yet (Add to the to-book list on Schedule check). It waits in To book on the detailed job list and in Arrange on Work, and on no engineer’s run; setting a date under Visit details books it, and Unbook puts a booked check back. A to-book check made in error is called off with Cancel check on its own page, which asks first; a booked check is cancelled from Edit, under Status. Book and Reschedule on the check page note a date in the past before you save: it is allowed, for logging a visit that already happened, and the visit shows as Visit overdue until the check is completed.
  • Past checks imported from another system (Import CSV on Gas safety checks, or Extract details on an archived certificate) are Completed, read-only history: the check page says where the check came from, who imported it and when, the list shows Imported in its Origin column, it offers no Edit in the list or on its page, and Manifold never issues a certificate from it. The engineer shows as the name the old system recorded, marked (imported), until an owner links that name to a person under Engineers; the recorded name itself never changes.
  • Generation is refused when a trial or subscription has lapsed; the message names the reason so the owner knows what to change. The plan’s monthly records allowance never stops a certificate for a visit that has been done: past the allowance the certificate is still issued, and the owner and office are warned as it fills (see Billing, Plans, and Entitlements).
  • A check that has an issued certificate cannot be cancelled. Setting it to Cancelled is refused with a message that the certificate stands; if the certificate was issued in error, book a new check and issue a replacement. A check with no certificate can still be cancelled. Once a check is submitted, or has a certificate, its property, engineer and visit date and times are fixed, because the certificate states them: the edit page shows them without letting them change, and a change is refused with the reason. A defect raised on a check stays at that check’s property. The edit page is headed by the check’s status: Edit scheduled check for a booked one, Edit check on the to-book list for one with no date yet, and Edit check for any other.
  • The Engineer filter on the Gas safety checks list names everyone a check is or can be assigned to, each once: your engineers, the owner or an office user who does visits, and anyone since made inactive who still holds a check. It ends with Unassigned, for the checks nobody holds. A saved report keeps Unassigned as no engineer. Search on Gas safety checks finds a check by address, reference or engineer: type part of an engineer’s name or email. The engineer is always who did the work, the same one the list’s Engineer column shows (the issued record’s engineer, else the person it is assigned to, else the typed name), so the search and the Engineer filter find a check under that name and under no other. If the From date is after the To date, the list says so instead of showing nothing. The Scheduled from and to range, and the Date column’s sort, work on the date a check is scheduled for. The Date column leads with the scheduled date, so the column, the filter and the sort are on the same date. A check done on a different day shows Checked and the day it was carried out under it, so a check scheduled for 1 Oct and done on 16 Oct sits in a list that ends on 1 Oct, reads 1 Oct 2026 with Checked 16 Oct 2026 under it, and says why. Booking a check on a property that already has another open check is allowed, as a recall or second visit can need it, but the save says so, so you can check you do not need both; the check’s own page keeps saying so for as long as the other check is open.

Record Quality

  • Every record should identify the property, client, engineer, Gas Safe number, appliances checked, and outcome.
  • No record is made without the engineer’s Gas Safe licence number: the one on the check, or else the one on the engineer’s profile. When neither is there, the check page says so under Generate, and the engineer’s phone asks for it before Submit; the first number typed on a check is saved to their profile, so it is asked for once.
  • Defects should carry clear severity and remedial guidance before the record is shared.
  • Records are immutable once generated, so review carefully before generating.
  • Before you generate, the check page lists appliance data that would print on the certificate as typed, each against its appliance: a GC number that is not 7 digits, or a reading outside what an instrument could show. It is a warning, not a block, because the figures are the engineer’s record and the office cannot edit them from there: send the check back to the engineer to put right (see Changing a check before its certificate).
  • Generating any certificate for a property marked as no longer ours restores it: doing the work makes it yours again, so it returns to every list, count and reminder.
  • Record PDFs use a fixed Manifold document palette so they render consistently outside the console theme.

Troubleshooting

  • Record will not generate: confirm the engineer has signed it (a check sent back to them waits for their signature), the overall result is set, every appliance has a result (or the result is Unable to complete), a Satisfactory verdict has no unsafe appliance, no senior review is open, for a CP12 the landlord or agent has an address (the reason links to the client to add it; a check booked without a client uses its property’s) and, for a CP12 from a visit on or after 1 November 2026, the gas tightness test result is recorded (Not applicable counts), and the check date is not after today (a check is dated the day of the visit, so correct the date on the check). A visit where access was not gained never makes a certificate: it is closed as a no-access visit and the property stays due, so book another visit. The wasted journey can still be charged: Invoice the no-access visit, at the top of the check page, starts its invoice (see Invoices).
  • Record looks wrong: it cannot be edited, deleted or regenerated once generated. An owner or office user opens it and chooses Issue a replacement, which opens a corrected copy of its check for the engineer to put right and sign again. The record that check makes replaces the old one (see Replacing a record).
  • Duplicate record: generation is idempotent per check and certificate type, so repeating it opens the existing record rather than minting another; a check can still carry a CP14 warning notice alongside its CP12.

Changing a check before its certificate

The readings, results, defects and signatures on a check are the engineer’s, signed by them. The office changes its own details itself, and sends anything the engineer recorded back to them to put right and sign again.

  • Send back to the engineer: on a submitted check with no certificate yet, the Send back to the engineer card under Engineer findings asks what they should change. Send back puts the check In progress, adds your note to the check’s Notes with the date, which the engineer sees at the top of the check on their phone, and sends them a notification. Their signature is cleared, so they put it right, sign and submit again. It works whether or not your firm uses senior review; a check already in senior review uses Request changes there instead.
  • The office’s own details stay editable until the certificate is made: Edit on a submitted or in-progress check changes its Notes, the office-only note and the renewal date. Its property, engineer and visit date are fixed once it is submitted. The landlord or agent, the property address and the tenant are read from the property and client when the certificate is made, so correct them there, from the Property and Client links under Visit details.
  • Only the engineer a check is assigned to signs it. An owner or office user who opens a colleague’s check with Record on mobile sees no signature pad and not the engineer’s signature: their Submit saves their changes and sends the check back to the engineer to check and sign, and says so.
  • A check assigned to an engineer makes no certificate until it carries that engineer’s signature. Generate says why while it is with the engineer.

Senior Review

For apprentice, second-engineer, or sensitive jobs, a check can be routed through a senior review before its certificate exists. The engineer ticks Request review when I submit, and the record stays held until the office signs it off.

  • A review moves through requested, changes requested, approved, or cancelled, with a note in each direction.
  • While a review is open, record generation is blocked; approving or cancelling the review releases it, and requesting changes sets the check to Action required until the engineer resubmits. On the Gas safety checks list and the check page the office sees Awaiting senior review and Changes requested, and the reason under Generate links straight to the Senior review card. Under Engineer findings the reviewer sees what the certificate will print: the fuel, the gas tightness test line, any LPG supply, and the engineer’s and tenant’s signatures.
  • The office reviews from the Senior review card on the check page: Approve release, Request changes (a reviewer note is required) or Cancel review. Manifold Assist can draft the reviewer note on plans that include it, and the office can also request a review itself after a check is submitted.

Troubleshooting

  • Record button blocked with a review message: approve the review, request changes, or cancel it from the check detail page.
  • Review request missing: the engineer ticks Request review when I submit before submitting, or the office requests one from the Senior review card on the check page.
  • No Senior review card or option at all: the owner has switched senior review off under Settings, Organisation, Features your firm uses (or the engineer works alone). A new request is refused with Senior review is switched off for your firm; a review already open still shows so it can be finished. Switch it back on there to use it again.

Review Before You Generate

Records are immutable once created, so the review step is where quality is enforced. Generate only when the appliance results, defects, photos, and signatures tell a complete and defensible story.

  • Confirm each appliance has the readings its type requires.
  • Confirm defect categories (AR, ID, NCS) and remedial actions are correct.
  • Confirm the engineer signature is present and the certificate identity is right.
  • Resolve anything ambiguous with the engineer before generating, not after.

Why Immutability Helps

A record that cannot be quietly edited after the fact is what makes it trustworthy evidence. Manifold leans into this: generation is idempotent per check, and corrections happen by completing a new check from corrected source data rather than by editing or regenerating the record.

Troubleshooting

  • If a record is wrong, do not look for an edit or regenerate button; correct the source data and complete a new check, which produces a new record.
  • If a record pack is missing a certificate, confirm each underlying check has generated its record.
  • If generation is blocked, read the reason after Not ready to generate under the button: the check is missing an overall result or an appliance result, a Satisfactory verdict has an unsafe appliance, a CP12 has no landlord or agent address, or a senior review is still open.

Was this page useful?